Timeline:      2019 - 2021
Location:      Garafraxa, Ontario
Description:

Rehabilitation of the Bridge No 7 included the installation of a temporary hanging access platform, concrete deck removal and replacement with composite wood concrete deck, handrail replacement, cross beam and hanging beams rehabilitation, and concrete sealing of the superstructure. The work was completed in phases and with extreme care due to the heritage classification of the structure.

Bridge No 7.jpg

CONCRETE DECK REMOVAL

Removal of concrete deck in phases to reduce stresses to bridge.

20191206_071223_edited.jpg

INSTALLATION OF HANGING ACCESS PLATFORM

Installation of work platform to complete rehabilitation works.

20190710_073051.jpg

COMPOSITE DECK INSTALLATION

A composite deck consisting of timber and concrete was installed to limit the weight of the deck.

IMG_20200916_163620_edited.jpg

INSTALLATION OF WATERPROOFING AND WEARING SURFACE

Installation of wearing surface included a three phase procedure of applying a specialty epoxy wearing surface which negated the need for asphalt.