CONESTOGA DAM REHABILITATION
Timeline: Phase 1-2019 Phase 2-2020
Location: Drayton, Ontario
Description:
Rehabilitation of the Conestaga Dam took places in two phases. The first phase was rehabilitation works to the downstream West wingwall, and the second was to the downstream East wingwall. Works in both phases included installation of temporary barge access system to access the 25m high wingwall.
BARGE ACCESS SYSTEM
Installation of barge access system including equipment to access the 25m high repairs.
PHASE 1 - WEST WINGWALL REPAIRS
Concrete rehabilitation works to the West wingwall.
PHASE 2 - EAST WINGWALL REPAIRS
Concrete rehabilitation works to the West wingwall.