GORDONVILLE BRIDGE REPLACEMENT
Timeline: 2018 to 2019
Location: Arthur, Ontario
Description:
Replacement of the Gordonville Bridge included the construction of a temporary bridge for equipment access, demolition of the existing bridge, and construction of a new 35m bridge.
INSTALLATION OF CONCRETE GIRDER
Installation of five, 35m girders including bearings and seats.
CONSTRUCTION OF ABUTMENT AND WINGWALLS
Concrete forming, placement, finishing and curing of abutments and wingwalls.
CONSTRUCTION OF CONCRETE DECK
Concrete forming, placement, finishing and curing of 35m bridge deck.